Ontario Community College - B2 (Demo Data) 1 window analyzed: Baseline → Current
Scheduled completion slipped 21 working days, from 31-Aug-2026 to 30-Sep-2026, measured across 1 window (01-Apr-2025 to 01-Jul-2025). Of that movement, the slip registers attribute 9 wd to the Owner, 12 wd to the Contractor; nothing remains unattributed. The finish driver at the final data date is A4240 (Minor Deficiencies & Touch-ups), at the end of the driving critical-path chain. On the critical path, 6 activities grew in scheduler-estimated duration (+24 wd) and 9 reduced (-304 wd); the full per-activity tables follow. 309 activities moved their finish dates over the period; every one is listed in the registers below, none omitted.
Windows Overview
per-window shift and cumulative vs baseline, working days| Window | Period | Shift (wd) | Cumulative vs Baseline (wd) | CP Activities | CP Duration Changes | Slipped Activities |
|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | +21 wd | +21 wd | 39 | 15 | 281 |
Window Shift Trend
signed completion shift per window (working days)Cumulative Attribution Summary
party share of project slip-daysConcurrent Delay Matrix
per-window × per-party attribution grid| Window | Period | Owner | Contractor | Concurrent | Force Majeure | Unattributed | Window Shift (wd) | Finish Driver |
|---|---|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | +9 wd | +12 wd | — | — | — | +21 wd | A4240 early_end_date |
| Cumulative | project totals | +9 wd | +12 wd | 0 wd | 0 wd | 0 wd | +21 wd | — |
Slip Velocity & Acceleration
per-window slip-rate trend| Window | Period | Duration (wd) | Shift (wd) | Velocity (wd/wd) | Δ Acceleration | Midpoint Date | Half-Period Slip (wd) |
|---|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | 62 wd | +21 wd | +0.339 | — | 16-May-2025 | +10.5 wd |
WOET — Worked-vs-On-time Execution Timeline
4-state day classification| Code | Activity | Baseline Period | Actual Period | Progress (wd) | Gain (wd) | Extended (wd) | Void (wd) |
|---|---|---|---|---|---|---|---|
| A1160 | TPO Roofing Shop Drawings | 2025-06-05 → 2025-06-19 | 2025-07-09 → 2025-08-26 | 0 wd | 0 wd | 35 wd | 11 wd |
| A3930 | Interior Demolition | 2025-06-13 → 2025-07-07 | 2025-07-21 → 2025-09-02 | 0 wd | 0 wd | 31 wd | 16 wd |
| A1460 | 23 25 00 - Water Treatment (R0) | 2025-06-26 → 2025-07-04 | 2025-06-26 → 2025-08-12 | 6 wd | 0 wd | 27 wd | 0 wd |
| A1280 | ACT Data sheet and Sample | 2025-07-11 → 2025-07-25 | 2025-07-23 → 2025-08-27 | 3 wd | 0 wd | 23 wd | 8 wd |
| A2500 | Install Rebar for Piers | 2025-07-31 → 2025-08-08 | 2025-07-29 → 2025-09-08 | 7 wd | 2 wd | 20 wd | 0 wd |
| A1120 | Cold-formed Metal Framing Shop Drawings | 2025-06-05 → 2025-06-19 | 2025-06-26 → 2025-07-23 | 0 wd | 0 wd | 19 wd | 11 wd |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 2025-06-05 → 2025-06-19 | 2025-06-20 → 2025-07-14 | 0 wd | 0 wd | 16 wd | 11 wd |
| A1090 | Masonry and Mortar Samples & Data Sheets | 2025-07-11 → 2025-07-25 | 2025-06-10 → 2025-08-18 | 11 wd | 22 wd | 16 wd | 0 wd |
| A2280 | Under Pinning Inspection | 2025-06-19 → 2025-06-20 | 2025-06-23 → 2025-07-14 | 0 wd | 0 wd | 15 wd | 2 wd |
| A2520 | Form and Pour Foundation Piers | 2025-08-08 → 2025-08-15 | 2025-08-11 → 2025-09-08 | 5 wd | 0 wd | 15 wd | 1 wd |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 2025-07-09 → 2025-07-23 | 2025-07-09 → 2025-08-12 | 11 wd | 0 wd | 14 wd | 0 wd |
| A2530 | Backfilling to U/S of Grade Beams | 2025-08-15 → 2025-08-22 | 2025-08-11 → 2025-09-12 | 6 wd | 4 wd | 14 wd | 0 wd |
| A1230 | Coiling Doors | 2025-07-11 → 2025-07-25 | 2025-08-05 → 2025-08-21 | 0 wd | 0 wd | 13 wd | 11 wd |
| A1580 | 26 50 00 - Lighting Fixtures | 2025-06-27 → 2025-07-14 | 2025-08-01 → 2025-08-18 | 0 wd | 0 wd | 12 wd | 11 wd |
| A1590 | 26 09 23 - Lighting Control (R0) | 2025-06-12 → 2025-06-26 | 2025-08-01 → 2025-08-18 | 0 wd | 0 wd | 12 wd | 11 wd |
| A1060 | Foundation Concrete Rebar Shop Drawing | 2025-06-05 → 2025-06-19 | 2025-05-29 → 2025-07-08 | 11 wd | 5 wd | 12 wd | 0 wd |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 2025-07-15 → 2025-07-29 | 2025-07-15 → 2025-08-14 | 11 wd | 0 wd | 12 wd | 0 wd |
| A1050 | Ductbank Underpinning Drawing | 2025-05-29 → 2025-06-12 | 2025-06-16 → 2025-06-30 | 0 wd | 0 wd | 11 wd | 11 wd |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 2025-06-27 → 2025-07-14 | 2025-06-27 → 2025-07-29 | 11 wd | 0 wd | 11 wd | 0 wd |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 2025-06-11 → 2025-06-24 | 2025-06-11 → 2025-07-08 | 10 wd | 0 wd | 9 wd | 0 wd |
| A1080 | Bentonite Waterstop Data Sheet | 2025-06-05 → 2025-06-19 | 2025-06-09 → 2025-07-02 | 9 wd | 0 wd | 8 wd | 2 wd |
| A1370 | 23 74 13 - Air Handling Units (R0) | 2025-06-26 → 2025-07-11 | 2025-06-26 → 2025-07-21 | 11 wd | 0 wd | 6 wd | 0 wd |
| A1290 | Suspended Metal Soffits | 2025-07-11 → 2025-07-25 | 2025-08-28 → 2025-09-04 | 0 wd | 0 wd | 5 wd | 11 wd |
| A1660 | Bentonite Waterstop | 2025-06-19 → 2025-06-26 | 2025-07-03 → 2025-07-09 | 0 wd | 0 wd | 5 wd | 6 wd |
| A1420 | 23 57 00 - Heat Exchangers | 2025-06-23 → 2025-06-25 | 2025-06-23 → 2025-07-03 | 3 wd | 0 wd | 5 wd | 0 wd |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 2025-07-11 → 2025-07-15 | 2025-07-11 → 2025-07-22 | 3 wd | 0 wd | 5 wd | 0 wd |
| A1070 | Foundation Concrete Mix Design | 2025-06-05 → 2025-06-19 | 2025-06-13 → 2025-06-25 | 5 wd | 0 wd | 4 wd | 6 wd |
| A1510 | 23 00 00 - Wall Fin Heater | 2025-07-22 → 2025-08-06 | 2025-07-22 → 2025-08-12 | 12 wd | 0 wd | 4 wd | 0 wd |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 2025-07-11 → 2025-07-25 | 2025-07-11 → 2025-07-31 | 11 wd | 0 wd | 4 wd | 0 wd |
| A1190 | Fire-resistive Material Data Sheet | 2025-06-19 → 2025-07-04 | 2025-06-27 → 2025-07-09 | 5 wd | 0 wd | 3 wd | 6 wd |
| A1150 | Built-up Roofing Shop Drawings | 2025-06-19 → 2025-07-04 | 2025-06-19 → 2025-07-09 | 11 wd | 0 wd | 3 wd | 0 wd |
| A1390 | 23 25 00 - Buffer Tanks | 2025-06-24 → 2025-06-27 | 2025-06-24 → 2025-07-03 | 4 wd | 0 wd | 3 wd | 0 wd |
| A1400 | 23 21 16 - Air Separator | 2025-06-24 → 2025-06-27 | 2025-06-24 → 2025-07-03 | 4 wd | 0 wd | 3 wd | 0 wd |
| A1410 | 23 21 16 - Expansion Tanks | 2025-06-24 → 2025-06-27 | 2025-06-24 → 2025-07-03 | 4 wd | 0 wd | 3 wd | 0 wd |
| A1220 | Flush Wood Doors Sample | 2025-07-11 → 2025-07-25 | 2025-08-26 → 2025-08-27 | 0 wd | 0 wd | 2 wd | 11 wd |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | 2025-06-05 → 2025-06-12 | 2025-06-10 → 2025-06-16 | 3 wd | 0 wd | 2 wd | 3 wd |
| A2260 | Top Soil Stripping | 2025-06-13 → 2025-06-18 | 2025-06-18 → 2025-06-20 | 1 wd | 0 wd | 2 wd | 3 wd |
| A2300 | Setup Hoarding @ Vestibule F100 | 2025-06-12 → 2025-06-16 | 2025-06-17 → 2025-06-18 | 0 wd | 0 wd | 2 wd | 3 wd |
| A2290 | Existing Structure Under Pinning | 2025-06-19 → 2025-07-11 | 2025-06-24 → 2025-07-15 | 13 wd | 0 wd | 2 wd | 3 wd |
| A2330 | Gas Meter and Pipe Relocation Investigation | 2025-06-12 → 2025-06-17 | 2025-06-17 → 2025-06-19 | 1 wd | 0 wd | 2 wd | 3 wd |
| A2340 | Gas Meter and pipe Relocation | 2025-06-17 → 2025-06-19 | 2025-06-20 → 2025-06-23 | 0 wd | 0 wd | 2 wd | 3 wd |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | 2025-06-18 → 2025-07-03 | 2025-06-23 → 2025-07-07 | 8 wd | 0 wd | 2 wd | 3 wd |
| A1020 | Subcontract Award | 2025-04-30 → 2025-05-29 | 2025-05-05 → 2025-06-02 | 18 wd | 0 wd | 2 wd | 3 wd |
| A1650 | Foundation Concrete Mix Design | 2025-06-19 → 2025-06-23 | 2025-06-26 → 2025-06-27 | 0 wd | 0 wd | 2 wd | 3 wd |
| A2370 | Bulk Excavation to U/S of Footings | 2025-07-11 → 2025-07-18 | 2025-07-16 → 2025-07-22 | 3 wd | 0 wd | 2 wd | 3 wd |
| A2320 | Demolition of Existing Vestibule F100 | 2025-06-16 → 2025-06-23 | 2025-06-18 → 2025-06-25 | 4 wd | 0 wd | 2 wd | 2 wd |
| A2230 | Ontario Community College Auto Show | 2025-04-30 → 2025-06-05 | 2025-06-09 → 2025-06-09 | 0 wd | 0 wd | 1 wd | 26 wd |
| A1680 IN-PROGRESS | Structural Steel | 2025-06-19 → 2025-07-25 | 2025-09-04 → — | 0 wd | 0 wd | 1 wd | 26 wd |
| A1130 IN-PROGRESS | Misc. Metals Shop Drawings | 2025-07-04 → 2025-07-18 | 2025-08-26 → — | 0 wd | 0 wd | 1 wd | 11 wd |
| A1330 IN-PROGRESS | Fall Arrest Anchors and Horizontal Lines | 2025-07-11 → 2025-07-25 | 2025-08-14 → — | 0 wd | 0 wd | 1 wd | 11 wd |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 2025-06-05 → 2025-06-19 | 2025-08-01 → 2025-08-01 | 0 wd | 0 wd | 1 wd | 11 wd |
| A1500 IN-PROGRESS | 23 52 16 - Heating Boilers | 2025-07-09 → 2025-07-23 | 2025-09-12 → — | 0 wd | 0 wd | 1 wd | 11 wd |
| A1040 | Permit (Not Required Per Ontario Community College) | 2025-05-12 → 2025-05-13 | 2025-05-16 → 2025-05-16 | 0 wd | 0 wd | 1 wd | 2 wd |
| A1010 | Contract Award | 2025-04-29 → 2025-04-30 | 2025-05-02 → 2025-05-02 | 0 wd | 0 wd | 1 wd | 2 wd |
| A1030 | IFC Drawings Released | 2025-05-09 → 2025-05-12 | 2025-05-15 → 2025-05-15 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2270 | Excavation for Under Pinning | 2025-06-18 → 2025-06-19 | 2025-06-23 → 2025-06-23 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2250 | Tree Removal, Protection and Equipment Mobilization | 2025-06-12 → 2025-06-13 | 2025-06-17 → 2025-06-17 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2310 | Relocate FAA | 2025-06-12 → 2025-06-16 | 2025-06-16 → 2025-06-17 | 1 wd | 0 wd | 1 wd | 2 wd |
| A3920 | Setup Temporary Hoarding | 2025-06-12 → 2025-06-13 | 2025-07-04 → 2025-07-04 | 0 wd | 0 wd | 1 wd | 2 wd |
| A3780 | Layout for Elevator Cylinder | 2025-06-18 → 2025-06-19 | 2025-06-23 → 2025-06-23 | 0 wd | 0 wd | 1 wd | 2 wd |
| A3790 | Drilling Elevator Cylinder from Grade | 2025-06-19 → 2025-06-20 | 2025-06-24 → 2025-06-24 | 0 wd | 0 wd | 1 wd | 2 wd |
| A3800 | Install Steel Casing into the ground | 2025-06-20 → 2025-06-23 | 2025-06-25 → 2025-06-25 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2380 | Bulk Excavation to U/S North Stair Footing | 2025-07-18 → 2025-07-21 | 2025-07-23 → 2025-07-23 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2510 | Supply of Embedment & Ankors | 2025-06-19 → 2025-06-20 | 2025-08-22 → 2025-08-22 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2600 | Compaction Inspection | 2025-04-01 → 2025-09-19 | 2025-08-15 → 2025-08-15 | 1 wd | 0 wd | 0 wd | 95 wd |
| A2390 | Subgrade Inspection | 2025-04-01 → 2025-07-25 | 2025-07-22 → 2025-07-22 | 1 wd | 0 wd | 0 wd | 77 wd |
| A3320 | Blocking Installation | 2025-04-01 → 2026-04-09 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A3480 | Blocking Installation | 2025-04-01 → 2026-04-23 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A3610 | Blocking Installation | 2025-04-01 → 2026-05-04 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A2660 | Install Temporary Hoarding for Slab on Deck | 2025-04-01 → 2025-11-03 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A3180 | Roof Inspection | 2025-04-01 → 2025-12-19 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A2620 | Structural Steel Inspection | 2025-04-01 → 2025-10-20 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | 2025-04-01 → 2026-02-25 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A3250 | Fire Spraying & Intumescent Paint Inspection | 2025-04-01 → 2026-02-25 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A2540 | Compaction Inspection | 2025-04-01 → 2025-08-22 | — → — | 0 wd | 0 wd | 0 wd | 63 wd |
| A2150 IN-PROGRESS | 26 50 00 - Lighting Fixtures | 2025-07-14 → 2025-11-20 | 2025-08-19 → — | 1 wd | 0 wd | 0 wd | 26 wd |
| A1180 IN-PROGRESS | Exterior Wall Cladding Shop Drawings | 2025-07-25 → 2025-08-11 | 2025-08-11 → — | 1 wd | 0 wd | 0 wd | 11 wd |
| A2450 | Rebar for Pad Footings | 2025-07-08 → 2025-07-29 | 2025-07-23 → 2025-07-24 | 2 wd | 0 wd | 0 wd | 11 wd |
| A1210 IN-PROGRESS | Interior Aluminum Screen | 2025-07-11 → 2025-07-25 | 2025-07-25 → — | 1 wd | 0 wd | 0 wd | 10 wd |
| A1170 | Air Barrier System Data Sheet and Mockup | 2025-06-19 → 2025-07-04 | — → — | 0 wd | 0 wd | 0 wd | 8 wd |
| A1700 | Cold-formed Metal Framing | 2025-06-19 → 2025-07-04 | — → — | 0 wd | 0 wd | 0 wd | 8 wd |
| A1740 | TPO Roofing (Bridge) | 2025-06-19 → 2025-08-04 | — → — | 0 wd | 0 wd | 0 wd | 8 wd |
| A1690 | Structural Reinforcement | 2025-06-19 → 2025-09-16 | — → — | 0 wd | 0 wd | 0 wd | 8 wd |
| A2140 IN-PROGRESS | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 2025-06-26 → 2025-11-05 | 2025-07-09 → — | 1 wd | 0 wd | 0 wd | 8 wd |
| A3940 | Existing Slab Removal and Trenching | 2025-06-12 → 2025-06-19 | — → — | 0 wd | 0 wd | 0 wd | 6 wd |
| A2160 IN-PROGRESS | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 2025-07-15 → 2026-04-21 | 2025-07-23 → — | 1 wd | 0 wd | 0 wd | 6 wd |
| A2420 IN-PROGRESS | Form and Pour North Exit Stair | 2025-07-29 → 2025-09-25 | 2025-08-04 → — | 1 wd | 0 wd | 0 wd | 4 wd |
| A1350 | Sprinkler & Standpipe Shop Drawings | 2025-06-26 → 2025-07-11 | — → — | 0 wd | 0 wd | 0 wd | 3 wd |
| A2180 | 26 09 23 - Lighting Control | 2025-06-26 → 2025-11-05 | — → — | 0 wd | 0 wd | 0 wd | 3 wd |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 2025-05-12 → 2025-05-13 | — → — | 0 wd | 0 wd | 0 wd | 2 wd |
| A1000 | Tender Closing | 2025-04-01 → 2025-04-29 | 2025-04-01 → 2025-04-29 | 20 wd | 0 wd | 0 wd | 0 wd |
| A2360 | Ductbank Shoring | 2025-07-03 → 2025-07-17 | 2025-06-23 → 2025-07-08 | 4 wd | 7 wd | 0 wd | 0 wd |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | 2025-07-07 → 2025-07-14 | 2025-07-07 → 2025-07-11 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1340 | Hydraulic Lift Shop Drawings | 2025-06-26 → 2025-07-11 | 2025-06-26 → 2025-07-09 | 9 wd | 0 wd | 0 wd | 0 wd |
| A1630 | Ductbank Underpinning | 2025-06-12 → 2025-06-19 | 2025-05-28 → 2025-05-28 | 0 wd | 1 wd | 0 wd | 0 wd |
| A1640 | Foundation Concrete Rebar | 2025-06-19 → 2025-07-04 | 2025-06-13 → 2025-06-13 | 0 wd | 1 wd | 0 wd | 0 wd |
| A1360 | 23 82 19 - Fan Coil Units (R0) | 2025-06-19 → 2025-07-04 | 2025-06-19 → 2025-07-03 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1380 | 23 21 23 - Pumps (R0) | 2025-06-24 → 2025-07-09 | 2025-06-24 → 2025-07-04 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1430 | 22 33 00 - Electric Domestic Water Heaters | 2025-06-19 → 2025-07-03 | 2025-06-19 → 2025-07-03 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1440 | 23 81 26 - Split System | 2025-06-12 → 2025-06-30 | 2025-06-12 → 2025-06-30 | 13 wd | 0 wd | 0 wd | 0 wd |
| A1450 | 22 13 29 - Sump Pumps (R0) | 2025-06-09 → 2025-06-20 | 2025-05-27 → 2025-06-02 | 0 wd | 5 wd | 0 wd | 0 wd |
| A1480 | 23 00 00 - Exhaust Fans (R0) | 2025-07-22 → 2025-08-06 | 2025-07-22 → 2025-07-22 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1490 | 23 00 00 - Unit Heater | 2025-07-22 → 2025-08-06 | 2025-07-22 → 2025-07-22 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1520 IN-PROGRESS | 23 74 13 - Air Source Heat Pump | 2025-06-26 → 2025-07-10 | 2025-06-26 → — | 3 wd | 0 wd | 0 wd | 0 wd |
| A1980 IN-PROGRESS | 23 25 00 - Buffer Tanks | 2025-07-04 → 2025-12-24 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A1990 IN-PROGRESS | 23 21 16 - Air Separator | 2025-07-04 → 2025-11-11 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2000 IN-PROGRESS | 23 21 16 - Expansion Tanks | 2025-07-04 → 2025-11-11 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2010 IN-PROGRESS | 23 57 00 - Heat Exchangers | 2025-07-04 → 2025-11-11 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2020 IN-PROGRESS | 22 33 00 - Electric Domestic Water Heaters | 2025-07-04 → 2025-11-12 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2030 IN-PROGRESS | 23 81 26 - Split System | 2025-07-10 → 2025-11-18 | 2025-07-10 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2040 IN-PROGRESS | 22 13 29 - Sump Pumps | 2025-06-19 → 2025-08-08 | 2025-06-19 → — | 8 wd | 0 wd | 0 wd | 0 wd |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | 2025-06-11 → 2025-06-24 | 2025-06-11 → 2025-06-17 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2190 IN-PROGRESS | 28 31 00 - Fire Alarm | 2025-06-26 → 2025-11-05 | 2025-06-18 → — | 3 wd | 6 wd | 0 wd | 0 wd |
| A2400 | Subgrade Preparation | 2025-07-25 → 2025-07-28 | 2025-07-23 → 2025-07-23 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2410 | Soil Bearing Capacity Inspection | 2025-07-28 → 2025-07-29 | 2025-07-24 → 2025-07-24 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | 2025-07-25 → 2025-07-28 | 2025-07-23 → 2025-07-23 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2460 | Rebar Inspection | 2025-07-29 → 2025-07-30 | 2025-07-25 → 2025-07-25 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | 2025-07-30 → 2025-07-31 | 2025-07-28 → 2025-07-28 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2490 | Concrete Field Testing | 2025-07-30 → 2025-07-31 | 2025-07-28 → 2025-07-28 | 0 wd | 1 wd | 0 wd | 0 wd |
Float Burndown Across Windows
per-activity float-erosion register, drawing-sheet exhibitCriticality predates the window: 38 of 99 activities opened at TF ≤ 0 at Baseline, and 14 more demonstrably burned their float to zero as completion moved 21 working days later
Total float in working days (wd), read from the schedule of record at 2 CPM snapshots, Baseline through Current spanning 1 window, day math on the project working calendar. Criticality test: TF ≤ 0. Sign convention: negative Δ = float lost across the window. Finish driver A4240; completion Baseline → Current: 21 wd later. Register bands: TF ≤ 0 · 1-5 wd (near-critical) · 6-20 wd · over 20 wd.
36 further activities first appear with one observation only. No second reading exists, so a loss of float cannot be demonstrated for them and is not claimed here.
conservation: 38 + 14 + 36 + 11 = 99 · reconciles to the register below
Reading notes
- Not plotted above: 49 activities with zero net float movement · 35 held TF ≤ 0 at every observation (11 observed at multiple snapshots, 24 single-observation) · 14 held constant positive float. All 99 appear in the register below.
- Baseline band counts in the inset carry the register convention: the 36 single-observation entrants are imputed at their only reading. The movement panel plots observed pairs only.
- The horizontal scale breaks at 40 wd, marked with a drafting section break. Nothing is clipped: A2480 reaches 315 wd on the compressed segment.
- Band deltas conserve across the population: −13 − 10 + 22 + 1 = 0 over 99 activities.
- Engine-reported recovery events (TF increase between consecutive snapshots): 35.
- Method caveat (cite in any expert report): Float burndown is post-processing of analyst-supplied CPM snapshots. Accuracy depends on the quality of the underlying schedule updates. Recovery events (TF increase) may reflect legitimate scope removal, schedule optimization, or activity deletion, and the analyst must verify which. Slip velocity is a linear average; actual burndown may be non-linear. The per-activity float-timeline presentation is not yet published in AACE/SCL literature; it is disclosed here as a CPP enhancement to the cited observational method.
Activity register · all 99 activities TF FIRST / LAST · Δ · FIRST AT TF ≤ 0
| Activity | TF at Baseline (wd) | TF at Current (wd) | Δ (wd) | First at TF ≤ 0 | Movement |
|---|---|---|---|---|---|
| A1000 | 2 | 2 | 0 | never | single observation |
| A1010 | 2 | 2 | 0 | never | single observation |
| A1020 | 2 | 2 | 0 | never | single observation |
| A1060 | 2 | 2 | 0 | never | single observation |
| A1110.1 | 0 | 0 | 0 | Current | single observation |
| A1640 | 2 | 2 | 0 | never | single observation |
| A1690 | 7 | 0 | −7 | Current | lost |
| A2230 | 5 | 5 | 0 | never | single observation |
| A2240 | 5 | 5 | 0 | never | single observation |
| A2290 | 5 | 5 | 0 | never | single observation |
| A2300 | 5 | 5 | 0 | never | single observation |
| A2310 | 5 | 5 | 0 | never | single observation |
| A2320 | 5 | 5 | 0 | never | single observation |
| A2370 | 5 | 5 | 0 | never | single observation |
| A2390 | 0 | 0 | 0 | Baseline | single observation |
| A2400 | 0 | 0 | 0 | Baseline | single observation |
| A2430 | 0 | 0 | 0 | Baseline | single observation |
| A2440 | 5 | 14 | +9 | never | gained |
| A2450 | 0 | 0 | 0 | Baseline | single observation |
| A2460 | 0 | 0 | 0 | Baseline | single observation |
| A2470 | 0 | 0 | 0 | Baseline | single observation |
| A2480 | 5 | 315 | +310 | never | gained |
| A2490 | 0 | 0 | 0 | Baseline | single observation |
| A2500 | 0 | 0 | 0 | Baseline | single observation |
| A2520 | 0 | 0 | 0 | Baseline | single observation |
| A2530 | 0 | 0 | 0 | Baseline | single observation |
| A2540 | 0 | 20 | +20 | Baseline | gained |
| A2550 | 0 | 14 | +14 | Baseline | gained |
| A2560 | 3 | 42 | +39 | never | gained |
| A2570 | 0 | 39 | +39 | Baseline | gained |
| A2580 | 4 | 16 | +12 | never | gained |
| A2590 | 0 | 16 | +16 | Baseline | gained |
| A2610 | 0 | 12 | +12 | Baseline | gained |
| A2620 | 0 | 12 | +12 | Baseline | gained |
| A2650 | 0 | 12 | +12 | Baseline | gained |
| A2660 | 0 | 12 | +12 | Baseline | gained |
| A2670 | 0 | 12 | +12 | Baseline | gained |
| A2680 | 0 | 12 | +12 | Baseline | gained |
| A2690 | 0 | 12 | +12 | Baseline | gained |
| A2700 | 0 | 12 | +12 | Baseline | gained |
| A2710 | 0 | 12 | +12 | Baseline | gained |
| A2740 | 4 | 4 | 0 | never | no movement |
| A2750 | 0 | 0 | 0 | Baseline | no movement |
| A2880 | 0 | 0 | 0 | Baseline | no movement |
| A2970 | 0 | 0 | 0 | Baseline | no movement |
| A3060 | 0 | 0 | 0 | Baseline | no movement |
| A3070 | 5 | 10 | +5 | never | gained |
| A3210 | 0 | 21 | +21 | Baseline | gained |
| A3220 | 0 | 21 | +21 | Baseline | gained |
| A3240 | 5 | 0 | −5 | Current | lost |
| A3250 | 5 | 0 | −5 | Current | lost |
| A3260 | 5 | 0 | −5 | Current | lost |
| A3280 | 5 | 15 | +10 | never | gained |
| A3290 | 0 | 15 | +15 | Baseline | gained |
| A3450 | 0 | 15 | +15 | Baseline | gained |
| A3580 | 0 | 15 | +15 | Baseline | gained |
| A3590 | 0 | 15 | +15 | Baseline | gained |
| A3610 | 0 | 15 | +15 | Baseline | gained |
| A3630 | 0 | 15 | +15 | Baseline | gained |
| A3640 | 0 | 15 | +15 | Baseline | gained |
| A3650 | 0 | 15 | +15 | Baseline | gained |
| A3660 | 5 | 20 | +15 | never | gained |
| A3670 | 0 | 15 | +15 | Baseline | gained |
| A3710 | 0 | 15 | +15 | Baseline | gained |
| A3720 | 5 | 20 | +15 | never | gained |
| A3750 | 0 | 15 | +15 | Baseline | gained |
| A3760 | 0 | 15 | +15 | Baseline | gained |
| A4030 | 119 | 0 | −119 | Current | lost |
| A4040 | 12 | 0 | −12 | Current | lost |
| A4040x | 0 | 0 | 0 | Current | single observation |
| A4050 | 184 | 0 | −184 | Current | lost |
| A4060 | 128 | 0 | −128 | Current | lost |
| A4070 | 133 | 0 | −133 | Current | lost |
| A4080 | 12 | 0 | −12 | Current | lost |
| A4090 | 12 | 0 | −12 | Current | lost |
| A4100 | 12 | 0 | −12 | Current | lost |
| A4110 | 12 | 0 | −12 | Current | lost |
| A4120 | 12 | 0 | −12 | Current | lost |
| A4170 | 16 | 5 | −11 | never | lost |
| A4180 | 0 | 0 | 0 | Baseline | no movement |
| A4190 | 0 | 0 | 0 | Baseline | no movement |
| A4200 | 0 | 0 | 0 | Baseline | no movement |
| A4210 | 0 | 0 | 0 | Baseline | no movement |
| A4220 | 5 | 5 | 0 | never | no movement |
| A4240 | 0 | 0 | 0 | Baseline | no movement |
| A4250 | 0 | 0 | 0 | Baseline | no movement |
| A4260 | 0 | 0 | 0 | Baseline | no movement |
| A4400 | 0 | 0 | 0 | Current | single observation |
| A4420 | 0 | 0 | 0 | Current | single observation |
| A4430 | 0 | 0 | 0 | Current | single observation |
| A4450 | 0 | 0 | 0 | Current | single observation |
| A4460 | 0 | 0 | 0 | Current | single observation |
| A4470 | 0 | 0 | 0 | Current | single observation |
| A4480 | 0 | 0 | 0 | Current | single observation |
| A4490 | 0 | 0 | 0 | Current | single observation |
| A4500 | 0 | 0 | 0 | Current | single observation |
| A4520 | 0 | 0 | 0 | Current | single observation |
| A4590 | 0 | 0 | 0 | Current | single observation |
| A4820 | 0 | 0 | 0 | Current | single observation |
Cumulative Activity Slip Register
sum of signed slip across all windows| Code | Activity | Total Slip | Windows Touched |
|---|---|---|---|
| A4070 CP | Frames installation | +182 wd | 1 |
| A4060 CP | Blocking | +169 wd | 1 |
| A4050 CP | Sprinkler Rough-ins | +162 wd | 1 |
| A4030 CP | New Partition Framing | +136 wd | 1 |
| A3850 | Foundations | +126 wd | 1 |
| A3860 | Concrete Vertical Piers | +126 wd | 1 |
| A3870 | Removal of Existing Facade for Tie In | +126 wd | 1 |
| A3880 | Structural Steel erection including expansion plates | +94 wd | 1 |
| A3890 | Envelope | +94 wd | 1 |
| A4150 | New Exterior Paved Areas and Sidewalks | +94 wd | 1 |
| A4160 | Landscape Installations | +94 wd | 1 |
| A3940 | Existing Slab Removal and Trenching | +90 wd | 1 |
| A3900 | Interior M&E Rough in | +84 wd | 1 |
| A2090 | 23 52 16 - Heating Boilers | +71 wd | 1 |
| A3910 | Interior Finishes | +65 wd | 1 |
| A2730 | Stairs B Installation @ North Side | +62 wd | 1 |
| A1710 | Misc. Metals | +62 wd | 1 |
| A2720 | Tactile Attention Indicators Mock-up | +62 wd | 1 |
| A1500 | 23 52 16 - Heating Boilers | +62 wd | 1 |
| A1950 | 23 82 19 - Fan Coil Units | +62 wd | 1 |
| A2050 | 23 25 00 - Water Treatment | +61 wd | 1 |
| A2060 | 23 37 13 - Diffuser and Grilles | +60 wd | 1 |
| A3270 | New Stair A Installation | +59 wd | 1 |
| A2540 | Compaction Inspection | +58 wd | 1 |
| A2180 | 26 09 23 - Lighting Control | +55 wd | 1 |
| A3170 | Install Built-up Roof | +54 wd | 1 |
| A1130 | Misc. Metals Shop Drawings | +53 wd | 1 |
| A3180 | Roof Inspection | +52 wd | 1 |
| A1680 | Structural Steel | +48 wd | 1 |
| A1160 | TPO Roofing Shop Drawings | +47 wd | 1 |
| A1740 | TPO Roofing (Bridge) | +46 wd | 1 |
| A1330 | Fall Arrest Anchors and Horizontal Lines | +45 wd | 1 |
| A2640 | Install Roof Decking | +44 wd | 1 |
| A2630 | Install Roof Anchors | +44 wd | 1 |
| A1920 | Fall Arrest Anchors and Horizontal Lines | +44 wd | 1 |
| A3150 | Roof Parapet Framing | +44 wd | 1 |
| A3160 | Roof Penetration Layout | +44 wd | 1 |
| A2510 | Supply of Embedment & Ankors | +44 wd | 1 |
| A2580 | Underground Drainage | +43 wd | 1 |
| A2130 | 22 40 00 - Plumbing Fixtures | +42 wd | 1 |
| A3930 | Interior Demolition | +40 wd | 1 |
| A2590 | Backfilling to U/S of SOG | +39 wd | 1 |
| A1970 | 23 21 23 - Pumps | +38 wd | 1 |
| A1590 | 26 09 23 - Lighting Control (R0) | +36 wd | 1 |
| A2150 | 26 50 00 - Lighting Fixtures | +35 wd | 1 |
| A2220 | Testing and Inspection Cash Allowance Expenditure | +34 wd | 1 |
| A1960 | 23 74 13 - Air Handling Units | +34 wd | 1 |
| A2440 | Formwork Remaining Pad Footing (Ramp) | +34 wd | 1 |
| A4040 CP | MEP Rough-ins | +33 wd | 1 |
| A4080 CP | Drywall/Sheathing Installation | +33 wd | 1 |
| A4090 CP | Taping and mudding | +33 wd | 1 |
| A4110 CP | Tile and Rubber Flooring Installation | +33 wd | 1 |
| A4100 CP | Painting | +33 wd | 1 |
| A4120 CP | Final Terminations and Fixtures Installation | +33 wd | 1 |
| A2120 | 20 05 10 - Electric Heat Tracing | +33 wd | 1 |
| A4170 | Fire Alarm Verification | +32 wd | 1 |
| A1110 | Structural Reinforcement + Decking Shop Drawings | +30 wd | 1 |
| A1290 | Suspended Metal Soffits | +28 wd | 1 |
| A1820 | Coiling Doors | +28 wd | 1 |
| A1870 | ACT & ACB | +27 wd | 1 |
| A1460 | 23 25 00 - Water Treatment (R0) | +27 wd | 1 |
| A1580 | 26 50 00 - Lighting Fixtures | +25 wd | 1 |
| A1700 | Cold-formed Metal Framing | +24 wd | 1 |
| A1120 | Cold-formed Metal Framing Shop Drawings | +23 wd | 1 |
| A1220 | Flush Wood Doors Sample | +23 wd | 1 |
| A1280 | ACT Data sheet and Sample | +23 wd | 1 |
| A4240 CP | Minor Deficiencies & Touch-ups | +22 wd | 1 |
| A1810 | Flush Wood Doors | +22 wd | 1 |
| A4260 CP | Total Completion | +21 wd | 1 |
| A4220 | Final Cleaning | +21 wd | 1 |
| A4180 CP | Mechanical, Electrical and Elevator Commissioning | +21 wd | 1 |
| A4190 CP | Integrated Testing | +21 wd | 1 |
| A4250 CP | Ready-To-Take Over | +21 wd | 1 |
| A4230 | Close-out Documents & Training | +21 wd | 1 |
| A4210 CP | Occupancy | +20 wd | 1 |
| A2500 | Install Rebar for Piers | +20 wd | 1 |
| A4200 CP | Substantial Performance | +19 wd | 1 |
| A1230 | Coiling Doors | +19 wd | 1 |
| A1180 | Exterior Wall Cladding Shop Drawings | +18 wd | 1 |
| A1210 | Interior Aluminum Screen | +18 wd | 1 |
| A1760 | Exterior Wall Cladding | +18 wd | 1 |
| A1800 | Interior Aluminum Screens | +17 wd | 1 |
| A1090 | Masonry and Mortar Samples & Data Sheets | +16 wd | 1 |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | +16 wd | 1 |
| A2550 | Form and Pour Grade Beams | +16 wd | 1 |
| A2560 | Below Grade Vapour Barrier Mock-up | +16 wd | 1 |
| A2570 | Footing Vapor Barrier & Insulation | +16 wd | 1 |
| A2750 CP | L1, L2 & L3 Framing and Sheathing Installation | +15 wd | 1 |
| A2880 CP | L1, L2 & L3 Framing and Sheathing Installation | +15 wd | 1 |
| A2890 | L1 Masonry Wall Installation | +15 wd | 1 |
| A2770 | L1 Masonry Wall installation | +15 wd | 1 |
| A2790 | L1, L2 & L3 Air Vapour Barrier Installation | +15 wd | 1 |
| A3260 CP | Seal Concrete Floor | +15 wd | 1 |
| A3430 | Seal concrete Floor | +15 wd | 1 |
| A3280 | New partition framing | +15 wd | 1 |
| A3330 | Door frames Installation | +15 wd | 1 |
| A3440 | New partition framing | +15 wd | 1 |
| A3560 | Seal concrete Floor | +15 wd | 1 |
| A1670 | Masonry and Mortar | +15 wd | 1 |
| A3420 | Fire Spraying & Intumescent Paint | +15 wd | 1 |
| A3550 | Fire Spraying & Intumescent Paint | +15 wd | 1 |
| A2820 | Glazing Site Measure and Scanning | +15 wd | 1 |
| A2280 | Under Pinning Inspection | +15 wd | 1 |
| A2760 | Masonry Mock-up | +15 wd | 1 |
| A2740 | Cold-Formed Metal Framing Mock | +15 wd | 1 |
| A3680 | Misc. Metals Mock-up | +15 wd | 1 |
| A2780 | Above Grade Vapour Mock-up | +15 wd | 1 |
| A2800 | AVB Inspection | +15 wd | 1 |
| A3250 CP | Fire Spraying & Intumescent Paint Inspection | +15 wd | 1 |
| A2520 | Form and Pour Foundation Piers | +15 wd | 1 |
| A3490 | Door frames Installation | +14 wd | 1 |
| A3520 | Door and Hardware Installation | +14 wd | 1 |
| A3620 | Door frames Installation | +14 wd | 1 |
| A3570 | New wall partition framing | +14 wd | 1 |
| A3920 | Setup Temporary Hoarding | +14 wd | 1 |
| A3240 CP | Fire Spraying & Intumescent Paint | +14 wd | 1 |
| A3210 | Electrical and Mechanical Room | +14 wd | 1 |
| A3690 | Misc. Metals installation | +14 wd | 1 |
| A3220 | Mech. and Elec. Equipment Installation | +14 wd | 1 |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | +14 wd | 1 |
| A2530 | Backfilling to U/S of Grade Beams | +14 wd | 1 |
| A1060 | Foundation Concrete Rebar Shop Drawing | +12 wd | 1 |
| A1050 | Ductbank Underpinning Drawing | +12 wd | 1 |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | +12 wd | 1 |
| A3410 | Painting | +11 wd | 1 |
| A3300 | Electrical, FA & Comms rough-ins | +11 wd | 1 |
| A3320 | Blocking Installation | +11 wd | 1 |
| A3350 | Gypsum board Installation | +11 wd | 1 |
| A3360 | Drywall Taping and Mudding | +11 wd | 1 |
| A3390 | Interior Aluminum/Glazing Screens Installation | +11 wd | 1 |
| A3370 | Door and Hardware Installation | +11 wd | 1 |
| A3810 | Install Controller at Machine Room | +11 wd | 1 |
| A3820 | Rails and Elevator Car installation | +11 wd | 1 |
| A3830 | Power to controller, Phone lines and Comms | +11 wd | 1 |
| A3840 | Elevator Testing and Commissioning | +11 wd | 1 |
| A3380 | Interior Aluminum/Glazing Screens Mock-up | +11 wd | 1 |
| A3340 | ACT Baffles Mock-ups | +11 wd | 1 |
| A3400 | Paint Mock-up | +11 wd | 1 |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | +11 wd | 1 |
| A3290 | Mech. & Plumbing rough-ins | +10 wd | 1 |
| A3310 | Sprinkler Rough-ins | +10 wd | 1 |
| A3540 | Painting | +9 wd | 1 |
| A2610 | Erect Structural Steel | +9 wd | 1 |
| A2650 | Install Level 2 & 3 Decking | +9 wd | 1 |
| A3450 | Mech. & Plumbing rough-ins | +9 wd | 1 |
| A3480 | Blocking Installation | +9 wd | 1 |
| A3500 | Gypsum board Installation | +9 wd | 1 |
| A3460 | Electrical, FA & Comms rough-ins | +9 wd | 1 |
| A3510 | Drywall Taping and Mudding | +9 wd | 1 |
| A3530 | Interior Glazing Installation | +9 wd | 1 |
| A3590 | Electrical, FA & Comms rough-ins | +9 wd | 1 |
| A3580 | Mech. & Plumbing rough-ins | +9 wd | 1 |
| A3610 | Blocking Installation | +9 wd | 1 |
| A3470 | Sprinkler Rough-ins | +9 wd | 1 |
| A3600 | Sprinkler Rough-ins | +9 wd | 1 |
| A2660 | Install Temporary Hoarding for Slab on Deck | +9 wd | 1 |
| A2620 | Structural Steel Inspection | +9 wd | 1 |
| A1080 | Bentonite Waterstop Data Sheet | +8 wd | 1 |
| A1660 | Bentonite Waterstop | +8 wd | 1 |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | +8 wd | 1 |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | +7 wd | 1 |
| A3750 | Washroom Partitions and Accessories Installation | +6 wd | 1 |
| A2670 | Rebar and Prep Work for Slab on Deck | +6 wd | 1 |
| A3110 | L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) | +6 wd | 1 |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | +6 wd | 1 |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | +6 wd | 1 |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | +6 wd | 1 |
| A3720 | Ceiling/Wall Fixtures Installation | +6 wd | 1 |
| A3740 | Millwork Installation | +6 wd | 1 |
| A3710 | Tiling and rubber flooring Installation | +6 wd | 1 |
| A3670 | Painting | +6 wd | 1 |
| A3770 | Corner Guards and Wall Protection Installation | +6 wd | 1 |
| A3660 | Interior Glazing Installation | +6 wd | 1 |
| A3650 | Door and Hardware Installation | +6 wd | 1 |
| A3630 | Gypsum board Installation | +6 wd | 1 |
| A3640 | Drywall Taping and Mudding | +6 wd | 1 |
| A2850 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A2940 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A3020 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A3100 | Glazing Shop Fabrication | +6 wd | 1 |
| A3120 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A3760 | Plumbing Washroom Fixtures Installation | +6 wd | 1 |
| A3730 | Millwork Mock-up | +6 wd | 1 |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | +6 wd | 1 |
| A3700 | Tiling & Rubber & Carpet Flooring Mock-up | +6 wd | 1 |
| A1370 | 23 74 13 - Air Handling Units (R0) | +6 wd | 1 |
| A2030 | 23 81 26 - Split System | +6 wd | 1 |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | +6 wd | 1 |
| A2680 | Concrete pour for slab on deck level 2 & 3 | +5 wd | 1 |
| A2960 | L2 & L3 Cladding Installation (EW2) | +5 wd | 1 |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | +5 wd | 1 |
| A3040 | L2 & L3 Cladding Installation (EW2) | +5 wd | 1 |
| A3050 | Horizontal Shading Louvers | +5 wd | 1 |
| A2900 | Air Vapor Barrier Installation | +5 wd | 1 |
| A3140 | L1, L2 & L3 Cladding Installation (EW2, EW2A) | +5 wd | 1 |
| A3070 | L1, L2 & L3 Air Vapor Barrier Installation | +5 wd | 1 |
| A2690 | Final Grading and Vapor Barrier for SOG | +5 wd | 1 |
| A2860 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A2910 | Glazing Site Measure and Scanning | +5 wd | 1 |
| A2950 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A3000 | Glazing Shop Fabrication | +5 wd | 1 |
| A3030 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A3130 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | +5 wd | 1 |
| A1420 | 23 57 00 - Heat Exchangers | +5 wd | 1 |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | +5 wd | 1 |
| A2970 CP | L2 & L3 Framing and Sheathing Installation | +4 wd | 1 |
| A3060 CP | L1, L2 & L3 Framing and Sheathing Installation | +4 wd | 1 |
| A2980 | L2 & L3 Air Vapor Barrier Installation | +4 wd | 1 |
| A1070 | Foundation Concrete Mix Design | +4 wd | 1 |
| A1650 | Foundation Concrete Mix Design | +4 wd | 1 |
| A2830 | Glazing Shop Fabrication | +4 wd | 1 |
| A2920 | Glazing Shop Fabrication | +4 wd | 1 |
| A2990 | Glazing Site Measure and Scanning | +4 wd | 1 |
| A3090 | Glazing Site Measure and Scanning | +4 wd | 1 |
| A3230 | Fire Spraying & Intumescent Paint Mock-up | +4 wd | 1 |
| A1510 | 23 00 00 - Wall Fin Heater | +4 wd | 1 |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | +4 wd | 1 |
| A2100 | 23 00 00 - Wall Fin Heater | +4 wd | 1 |
| A1040 | Permit (Not Required Per Ontario Community College) | +3 wd | 1 |
| A1030 | IFC Drawings Released | +3 wd | 1 |
| A1150 | Built-up Roofing Shop Drawings | +3 wd | 1 |
| A1170 | Air Barrier System Data Sheet and Mockup | +3 wd | 1 |
| A1190 | Fire-resistive Material Data Sheet | +3 wd | 1 |
| A1350 | Sprinkler & Standpipe Shop Drawings | +3 wd | 1 |
| A1730 | Built-up Roofing | +3 wd | 1 |
| A1750 | Air Barrier System | +3 wd | 1 |
| A1770 | Fire-resistive Material | +3 wd | 1 |
| A1940 | Sprinkler & Standpipe Shop Drawings | +3 wd | 1 |
| A2710 | Concrete Pour and Curing for SOG | +3 wd | 1 |
| A2700 | Rebar Installation for SOG | +3 wd | 1 |
| A3190 | Hoisting Roof Equipment | +3 wd | 1 |
| A3200 | Roof Anchor System Installation | +3 wd | 1 |
| A1390 | 23 25 00 - Buffer Tanks | +3 wd | 1 |
| A1400 | 23 21 16 - Air Separator | +3 wd | 1 |
| A1410 | 23 21 16 - Expansion Tanks | +3 wd | 1 |
| A1520 | 23 74 13 - Air Source Heat Pump | +3 wd | 1 |
| A2110 | 23 74 13 - Air Source Heat Pump | +3 wd | 1 |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | +2 wd | 1 |
| A1010 | Contract Award | +2 wd | 1 |
| A2230 | Ontario Community College Auto Show | +2 wd | 1 |
| A2270 | Excavation for Under Pinning | +2 wd | 1 |
| A2250 | Tree Removal, Protection and Equipment Mobilization | +2 wd | 1 |
| A2260 | Top Soil Stripping | +2 wd | 1 |
| A2300 | Setup Hoarding @ Vestibule F100 | +2 wd | 1 |
| A2320 | Demolition of Existing Vestibule F100 | +2 wd | 1 |
| A2290 | Existing Structure Under Pinning | +2 wd | 1 |
| A2330 | Gas Meter and Pipe Relocation Investigation | +2 wd | 1 |
| A2340 | Gas Meter and pipe Relocation | +2 wd | 1 |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | +2 wd | 1 |
| A1020 | Subcontract Award | +2 wd | 1 |
| A1140 | Millwork Shop Drawings | +2 wd | 1 |
| A1200 | Hollow Metal Frames & Doors Shop Drawings | +2 wd | 1 |
| A1240 | Aluminum Framed Glazing System Shop Drawings | +2 wd | 1 |
| A1250 | Finished Hardware Schedule | +2 wd | 1 |
| A1260 | Stud framing and Gypsum Board Data Sheets | +2 wd | 1 |
| A1270 | Tiling Data sheet and samples | +2 wd | 1 |
| A1300 | Flooring Data Sheets and Samples | +2 wd | 1 |
| A1310 | Paint Drawdowns | +2 wd | 1 |
| A1320 | Washroom accessories and Partitions Shop Drawings | +2 wd | 1 |
| A1610 | Concrete Mix for Hardscapes | +2 wd | 1 |
| A1620 | Landscape Shop Drawings | +2 wd | 1 |
| A1720 | Millwork | +2 wd | 1 |
| A1780 | Hollow Metal Frames | +2 wd | 1 |
| A1830 | Aluminum Framed Glazing Systems | +2 wd | 1 |
| A1840 | Finished Hardware | +2 wd | 1 |
| A1850 | Stud framing & gypsum board | +2 wd | 1 |
| A1860 | Tiling | +2 wd | 1 |
| A1890 | Flooring | +2 wd | 1 |
| A1900 | Paint Drawdowns | +2 wd | 1 |
| A1910 | Washroom accessories and Partitions | +2 wd | 1 |
| A2200 | Concrete for Hardscape | +2 wd | 1 |
| A2210 | Landscape (unit pavers, furniture, etc) | +2 wd | 1 |
| A3780 | Layout for Elevator Cylinder | +2 wd | 1 |
| A3790 | Drilling Elevator Cylinder from Grade | +2 wd | 1 |
| A3800 | Install Steel Casing into the ground | +2 wd | 1 |
| A1690 CP | Structural Reinforcement | +2 wd | 1 |
| A1790 | Hollow Metal Doors | +2 wd | 1 |
| A2370 | Bulk Excavation to U/S of Footings | +2 wd | 1 |
| A2380 | Bulk Excavation to U/S North Stair Footing | +2 wd | 1 |
| A2310 | Relocate FAA | +1 wd | 1 |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | -1 wd | 1 |
| A1360 | 23 82 19 - Fan Coil Units (R0) | -1 wd | 1 |
| A1340 | Hydraulic Lift Shop Drawings | -2 wd | 1 |
| A1930 | Hydraulic Lift | -2 wd | 1 |
| A4010 | Underground Plumbing Rough-ins | -3 wd | 1 |
| A1380 | 23 21 23 - Pumps (R0) | -3 wd | 1 |
| A2390 | Subgrade Inspection | -3 wd | 1 |
| A2400 | Subgrade Preparation | -3 wd | 1 |
| A2410 | Soil Bearing Capacity Inspection | -3 wd | 1 |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | -3 wd | 1 |
| A2450 | Rebar for Pad Footings | -3 wd | 1 |
| A2460 | Rebar Inspection | -3 wd | 1 |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | -3 wd | 1 |
| A2490 | Concrete Field Testing | -3 wd | 1 |
| A2040 | 22 13 29 - Sump Pumps | -4 wd | 1 |
| A2360 | Ductbank Shoring | -7 wd | 1 |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | -7 wd | 1 |
| A2190 | 28 31 00 - Fire Alarm | -7 wd | 1 |
| A1480 | 23 00 00 - Exhaust Fans (R0) | -11 wd | 1 |
| A1490 | 23 00 00 - Unit Heater | -11 wd | 1 |
| A1640 | Foundation Concrete Rebar | -14 wd | 1 |
| A2420 | Form and Pour North Exit Stair | -14 wd | 1 |
| A1630 | Ductbank Underpinning | -16 wd | 1 |
| A1450 | 22 13 29 - Sump Pumps (R0) | -16 wd | 1 |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | -21 wd | 1 |
| A2080 | 23 00 00 - Unit Heater | -23 wd | 1 |
| A2600 | Compaction Inspection | -24 wd | 1 |
| A2070 | 23 00 00 - Exhaust Fans | -29 wd | 1 |
Window 1 — Baseline → Current
01-Apr-2025 → 01-Jul-2025 · shift +21 wd| Code | Activity | Prior Duration | Later Duration | Change (wd) |
|---|---|---|---|---|
| A3240 | Fire Spraying & Intumescent Paint | 5.0 wd | 15.0 wd | +10.0 wd |
| A4040 | MEP Rough-ins | 19.0 wd | 23.0 wd | +4.0 wd |
| A4030 | New Partition Framing | 10.0 wd | 13.0 wd | +3.0 wd |
| A4070 | Frames installation | 5.0 wd | 8.0 wd | +3.0 wd |
| A4050 | Sprinkler Rough-ins | 10.0 wd | 13.0 wd | +3.0 wd |
| A4240 | Minor Deficiencies & Touch-ups | 10.0 wd | 11.0 wd | +1.0 wd |
| A4200 | Substantial Performance | 1.0 wd | 0.0 wd | -1.0 wd |
| A4260 | Total Completion | 1.0 wd | 0.0 wd | -1.0 wd |
| A4210 | Occupancy | 1.0 wd | 0.0 wd | -1.0 wd |
| A4250 | Ready-To-Take Over | 1.0 wd | 0.0 wd | -1.0 wd |
| A4060 | Blocking | 10.0 wd | 7.0 wd | -3.0 wd |
| A2970 | L2 & L3 Framing and Sheathing Installation | 25.0 wd | 14.0 wd | -11.0 wd |
| A4080 | Drywall/Sheathing Installation | 38.0 wd | 10.0 wd | -28.0 wd |
| A1690 | Structural Reinforcement | 61.0 wd | 30.0 wd | -31.0 wd |
| A3250 | Fire Spraying & Intumescent Paint Inspection | 228.0 wd | 1.0 wd | -227.0 wd |
| Code | Activity | Prior Finish | Later Finish | Slip | Responsible Party | Cause Notes |
|---|---|---|---|---|---|---|
| A4070 CP | Frames installation | 30-Sep-2025 | 19-Jun-2026 | +182 wd | Contractor | Frame installation at the end of the delayed interior chain |
| A4060 CP | Blocking | 07-Oct-2025 | 09-Jun-2026 | +169 wd | Contractor | Blocking follows sprinkler rough-in in the interior chain |
| A4050 CP | Sprinkler Rough-ins | 07-Oct-2025 | 29-May-2026 | +162 wd | Contractor | Sprinkler rough-in follows partition framing; trade stacking on remobilization |
| A4030 CP | New Partition Framing | 23-Sep-2025 | 08-Apr-2026 | +136 wd | Contractor | Framing crew availability following remobilization |
| A3850 | Foundations | 22-Aug-2025 | 23-Feb-2026 | +126 wd | Owner | Differing site condition at the existing facade tie-in |
| A3860 | Concrete Vertical Piers | 29-Aug-2025 | 02-Mar-2026 | +126 wd | Owner | Follows delayed foundations at the tie-in |
| A3870 | Removal of Existing Facade for Tie In | 03-Sep-2025 | 05-Mar-2026 | +126 wd | Owner | Existing facade removal held for tie-in condition resolution |
| A3880 | Structural Steel erection including expansion plates | 10-Nov-2025 | 26-Mar-2026 | +94 wd | — | — |
| A3890 | Envelope | 15-Dec-2025 | 30-Apr-2026 | +94 wd | — | — |
| A4150 | New Exterior Paved Areas and Sidewalks | 14-Jan-2026 | 29-May-2026 | +94 wd | — | — |
| A4160 | Landscape Installations | 28-Jan-2026 | 12-Jun-2026 | +94 wd | — | — |
| A3940 | Existing Slab Removal and Trenching | 19-Jun-2025 | 28-Oct-2025 | +90 wd | Contractor | Resequenced slab removal and trenching |
| A3900 | Interior M&E Rough in | 14-Jan-2026 | 14-May-2026 | +84 wd | — | — |
| A2090 | 23 52 16 - Heating Boilers | 01-Dec-2025 | 16-Mar-2026 | +71 wd | — | — |
| A3910 | Interior Finishes | 11-Feb-2026 | 15-May-2026 | +65 wd | — | — |
| A2730 | Stairs B Installation @ North Side | 19-Nov-2025 | 18-Feb-2026 | +62 wd | — | — |
| A1710 | Misc. Metals | 29-Oct-2025 | 27-Jan-2026 | +62 wd | — | — |
| A2720 | Tactile Attention Indicators Mock-up | 30-Oct-2025 | 28-Jan-2026 | +62 wd | — | — |
| A1500 | 23 52 16 - Heating Boilers | 23-Jul-2025 | 21-Oct-2025 | +62 wd | — | — |
| A1950 | 23 82 19 - Fan Coil Units | 26-Nov-2025 | 25-Feb-2026 | +62 wd | — | — |
| A2050 | 23 25 00 - Water Treatment | 12-Nov-2025 | 09-Feb-2026 | +61 wd | — | — |
| A2060 | 23 37 13 - Diffuser and Grilles | 05-Dec-2025 | 05-Mar-2026 | +60 wd | — | — |
| A3270 | New Stair A Installation | 17-Nov-2025 | 10-Feb-2026 | +59 wd | — | — |
| A2540 | Compaction Inspection | 22-Aug-2025 | 14-Nov-2025 | +58 wd | — | — |
| A2180 | 26 09 23 - Lighting Control | 05-Nov-2025 | 23-Jan-2026 | +55 wd | — | — |
| A3170 | Install Built-up Roof | 17-Dec-2025 | 09-Mar-2026 | +54 wd | — | — |
| A1130 | Misc. Metals Shop Drawings | 18-Jul-2025 | 02-Oct-2025 | +53 wd | Contractor | Late misc. metals submittal |
| A3180 | Roof Inspection | 19-Dec-2025 | 09-Mar-2026 | +52 wd | — | — |
| A1680 | Structural Steel | 25-Jul-2025 | 02-Oct-2025 | +48 wd | — | — |
| A1160 | TPO Roofing Shop Drawings | 19-Jun-2025 | 26-Aug-2025 | +47 wd | Owner | Owner-directed revision to the roofing assembly; resubmittal and re-review cycle |
| A1740 | TPO Roofing (Bridge) | 04-Aug-2025 | 08-Oct-2025 | +46 wd | — | — |
| A1330 | Fall Arrest Anchors and Horizontal Lines | 25-Jul-2025 | 29-Sep-2025 | +45 wd | — | — |
| A2640 | Install Roof Decking | 12-Nov-2025 | 15-Jan-2026 | +44 wd | — | — |
| A2630 | Install Roof Anchors | 05-Nov-2025 | 08-Jan-2026 | +44 wd | — | — |
| A1920 | Fall Arrest Anchors and Horizontal Lines | 22-Oct-2025 | 23-Dec-2025 | +44 wd | — | — |
| A3150 | Roof Parapet Framing | 19-Nov-2025 | 22-Jan-2026 | +44 wd | — | — |
| A3160 | Roof Penetration Layout | 14-Nov-2025 | 19-Jan-2026 | +44 wd | — | — |
| A2510 | Supply of Embedment & Ankors | 20-Jun-2025 | 22-Aug-2025 | +44 wd | — | — |
| A2580 | Underground Drainage | 08-Sep-2025 | 07-Nov-2025 | +43 wd | — | — |
| A2130 | 22 40 00 - Plumbing Fixtures | 03-Dec-2025 | 03-Feb-2026 | +42 wd | — | — |
| A3930 | Interior Demolition | 07-Jul-2025 | 02-Sep-2025 | +40 wd | — | — |
| A2590 | Backfilling to U/S of SOG | 19-Sep-2025 | 14-Nov-2025 | +39 wd | — | — |
| A1970 | 23 21 23 - Pumps | 17-Nov-2025 | 12-Jan-2026 | +38 wd | — | — |
| A1590 | 26 09 23 - Lighting Control (R0) | 26-Jun-2025 | 18-Aug-2025 | +36 wd | — | — |
| A2150 | 26 50 00 - Lighting Fixtures | 20-Nov-2025 | 12-Jan-2026 | +35 wd | — | — |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 13-May-2025 | 02-Jul-2025 | +34 wd | — | — |
| A1960 | 23 74 13 - Air Handling Units | 30-Mar-2026 | 15-May-2026 | +34 wd | — | — |
| A2440 | Formwork Remaining Pad Footing (Ramp) | 30-Jul-2025 | 17-Sep-2025 | +34 wd | — | — |
| A4040 CP | MEP Rough-ins | 25-Mar-2026 | 11-May-2026 | +33 wd | Contractor | MEP rough-in trade coordination; stacked trades after remobilization |
| A4080 CP | Drywall/Sheathing Installation | 19-May-2026 | 06-Jul-2026 | +33 wd | — | — |
| A4090 CP | Taping and mudding | 02-Jun-2026 | 20-Jul-2026 | +33 wd | — | — |
| A4110 CP | Tile and Rubber Flooring Installation | 12-Jun-2026 | 30-Jul-2026 | +33 wd | — | — |
| A4100 CP | Painting | 05-Jun-2026 | 23-Jul-2026 | +33 wd | — | — |
| A4120 CP | Final Terminations and Fixtures Installation | 19-Jun-2026 | 06-Aug-2026 | +33 wd | — | — |
| A2120 | 20 05 10 - Electric Heat Tracing | 01-Dec-2025 | 19-Jan-2026 | +33 wd | — | — |
| A4170 | Fire Alarm Verification | 07-Jul-2026 | 20-Aug-2026 | +32 wd | — | — |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 19-Jun-2025 | 01-Aug-2025 | +30 wd | — | — |
| A1290 | Suspended Metal Soffits | 25-Jul-2025 | 04-Sep-2025 | +28 wd | — | — |
| A1820 | Coiling Doors | 03-Dec-2025 | 14-Jan-2026 | +28 wd | — | — |
| A1870 | ACT & ACB | 09-Sep-2025 | 17-Oct-2025 | +27 wd | — | — |
| A1460 | 23 25 00 - Water Treatment (R0) | 04-Jul-2025 | 12-Aug-2025 | +27 wd | — | — |
| A1580 | 26 50 00 - Lighting Fixtures | 14-Jul-2025 | 18-Aug-2025 | +25 wd | — | — |
| A1700 | Cold-formed Metal Framing | 04-Jul-2025 | 07-Aug-2025 | +24 wd | — | — |
| A1120 | Cold-formed Metal Framing Shop Drawings | 19-Jun-2025 | 23-Jul-2025 | +23 wd | — | — |
| A1220 | Flush Wood Doors Sample | 25-Jul-2025 | 27-Aug-2025 | +23 wd | — | — |
| A1280 | ACT Data sheet and Sample | 25-Jul-2025 | 27-Aug-2025 | +23 wd | — | — |
| A4240 CP | Minor Deficiencies & Touch-ups | 28-Aug-2026 | 30-Sep-2026 | +22 wd | Contractor | Deficiency and touch-up re-work extended by finishing crew quality issues |
| A1810 | Flush Wood Doors | 12-Nov-2025 | 12-Dec-2025 | +22 wd | — | — |
| A4260 CP | Total Completion | 31-Aug-2026 | 30-Sep-2026 | +21 wd | — | — |
| A4220 | Final Cleaning | 05-Aug-2026 | 03-Sep-2026 | +21 wd | — | — |
| A4180 CP | Mechanical, Electrical and Elevator Commissioning | 29-Jul-2026 | 27-Aug-2026 | +21 wd | — | — |
| A4190 CP | Integrated Testing | 12-Aug-2026 | 11-Sep-2026 | +21 wd | — | — |
| A4250 CP | Ready-To-Take Over | 31-Aug-2026 | 30-Sep-2026 | +21 wd | — | — |
| A4230 | Close-out Documents & Training | 05-Aug-2026 | 03-Sep-2026 | +21 wd | — | — |
| A4210 CP | Occupancy | 13-Aug-2026 | 11-Sep-2026 | +20 wd | — | — |
| A2500 | Install Rebar for Piers | 08-Aug-2025 | 08-Sep-2025 | +20 wd | — | — |
| A4200 CP | Substantial Performance | 14-Aug-2026 | 11-Sep-2026 | +19 wd | — | — |
| A1230 | Coiling Doors | 25-Jul-2025 | 21-Aug-2025 | +19 wd | — | — |
| A1180 | Exterior Wall Cladding Shop Drawings | 11-Aug-2025 | 05-Sep-2025 | +18 wd | — | — |
| A1210 | Interior Aluminum Screen | 25-Jul-2025 | 20-Aug-2025 | +18 wd | — | — |
| A1760 | Exterior Wall Cladding | 05-Nov-2025 | 01-Dec-2025 | +18 wd | — | — |
| A1800 | Interior Aluminum Screens | 03-Dec-2025 | 29-Dec-2025 | +17 wd | — | — |
| A1090 | Masonry and Mortar Samples & Data Sheets | 25-Jul-2025 | 18-Aug-2025 | +16 wd | — | — |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 19-Jun-2025 | 14-Jul-2025 | +16 wd | — | — |
| A2550 | Form and Pour Grade Beams | 08-Sep-2025 | 30-Sep-2025 | +16 wd | — | — |
| A2560 | Below Grade Vapour Barrier Mock-up | 09-Sep-2025 | 01-Oct-2025 | +16 wd | — | — |
| A2570 | Footing Vapor Barrier & Insulation | 12-Sep-2025 | 06-Oct-2025 | +16 wd | — | — |
| A2750 CP | L1, L2 & L3 Framing and Sheathing Installation | 05-Dec-2025 | 29-Dec-2025 | +15 wd | — | — |
| A2880 CP | L1, L2 & L3 Framing and Sheathing Installation | 19-Dec-2025 | 13-Jan-2026 | +15 wd | — | — |
| A2890 | L1 Masonry Wall Installation | 29-Dec-2025 | 20-Jan-2026 | +15 wd | — | — |
| A2770 | L1 Masonry Wall installation | 09-Dec-2025 | 31-Dec-2025 | +15 wd | — | — |
| A2790 | L1, L2 & L3 Air Vapour Barrier Installation | 12-Dec-2025 | 06-Jan-2026 | +15 wd | — | — |
| A3260 CP | Seal Concrete Floor | 04-Mar-2026 | 25-Mar-2026 | +15 wd | — | — |
| A3430 | Seal concrete Floor | 06-Mar-2026 | 27-Mar-2026 | +15 wd | — | — |
| A3280 | New partition framing | 18-Mar-2026 | 08-Apr-2026 | +15 wd | — | — |
| A3330 | Door frames Installation | 25-Mar-2026 | 15-Apr-2026 | +15 wd | — | — |
| A3440 | New partition framing | 01-Apr-2026 | 22-Apr-2026 | +15 wd | — | — |
| A3560 | Seal concrete Floor | 12-Mar-2026 | 02-Apr-2026 | +15 wd | — | — |
| A1670 | Masonry and Mortar | 04-Aug-2025 | 25-Aug-2025 | +15 wd | — | — |
| A3420 | Fire Spraying & Intumescent Paint | 04-Mar-2026 | 25-Mar-2026 | +15 wd | — | — |
| A3550 | Fire Spraying & Intumescent Paint | 11-Mar-2026 | 01-Apr-2026 | +15 wd | — | — |
| A2820 | Glazing Site Measure and Scanning | 08-Dec-2025 | 30-Dec-2025 | +15 wd | — | — |
| A2280 | Under Pinning Inspection | 20-Jun-2025 | 14-Jul-2025 | +15 wd | — | — |
| A2760 | Masonry Mock-up | 08-Dec-2025 | 30-Dec-2025 | +15 wd | — | — |
| A2740 | Cold-Formed Metal Framing Mock | 01-Dec-2025 | 22-Dec-2025 | +15 wd | — | — |
| A3680 | Misc. Metals Mock-up | 02-Apr-2026 | 23-Apr-2026 | +15 wd | — | — |
| A2780 | Above Grade Vapour Mock-up | 08-Dec-2025 | 30-Dec-2025 | +15 wd | — | — |
| A2800 | AVB Inspection | 08-Dec-2025 | 30-Dec-2025 | +15 wd | — | — |
| A3250 CP | Fire Spraying & Intumescent Paint Inspection | 25-Feb-2026 | 19-Mar-2026 | +15 wd | — | — |
| A2520 | Form and Pour Foundation Piers | 15-Aug-2025 | 08-Sep-2025 | +15 wd | — | — |
| A3490 | Door frames Installation | 07-Apr-2026 | 27-Apr-2026 | +14 wd | — | — |
| A3520 | Door and Hardware Installation | 21-Apr-2026 | 11-May-2026 | +14 wd | — | — |
| A3620 | Door frames Installation | 23-Apr-2026 | 13-May-2026 | +14 wd | — | — |
| A3570 | New wall partition framing | 16-Apr-2026 | 06-May-2026 | +14 wd | — | — |
| A3920 | Setup Temporary Hoarding | 13-Jun-2025 | 04-Jul-2025 | +14 wd | — | — |
| A3240 CP | Fire Spraying & Intumescent Paint | 25-Feb-2026 | 18-Mar-2026 | +14 wd | Owner | Fire-spray application held for owner inspector availability |
| A3210 | Electrical and Mechanical Room | 04-Mar-2026 | 24-Mar-2026 | +14 wd | — | — |
| A3690 | Misc. Metals installation | 29-May-2026 | 18-Jun-2026 | +14 wd | — | — |
| A3220 | Mech. and Elec. Equipment Installation | 18-Mar-2026 | 07-Apr-2026 | +14 wd | — | — |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 23-Jul-2025 | 12-Aug-2025 | +14 wd | — | — |
| A2530 | Backfilling to U/S of Grade Beams | 22-Aug-2025 | 12-Sep-2025 | +14 wd | — | — |
| A1060 | Foundation Concrete Rebar Shop Drawing | 19-Jun-2025 | 08-Jul-2025 | +12 wd | — | — |
| A1050 | Ductbank Underpinning Drawing | 12-Jun-2025 | 30-Jun-2025 | +12 wd | — | — |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 29-Jul-2025 | 14-Aug-2025 | +12 wd | — | — |
| A3410 | Painting | 07-May-2026 | 25-May-2026 | +11 wd | — | — |
| A3300 | Electrical, FA & Comms rough-ins | 06-Apr-2026 | 21-Apr-2026 | +11 wd | — | — |
| A3320 | Blocking Installation | 09-Apr-2026 | 24-Apr-2026 | +11 wd | — | — |
| A3350 | Gypsum board Installation | 16-Apr-2026 | 01-May-2026 | +11 wd | — | — |
| A3360 | Drywall Taping and Mudding | 30-Apr-2026 | 15-May-2026 | +11 wd | — | — |
| A3390 | Interior Aluminum/Glazing Screens Installation | 07-May-2026 | 25-May-2026 | +11 wd | — | — |
| A3370 | Door and Hardware Installation | 07-May-2026 | 25-May-2026 | +11 wd | — | — |
| A3810 | Install Controller at Machine Room | 08-May-2026 | 26-May-2026 | +11 wd | — | — |
| A3820 | Rails and Elevator Car installation | 25-May-2026 | 09-Jun-2026 | +11 wd | — | — |
| A3830 | Power to controller, Phone lines and Comms | 01-Jun-2026 | 16-Jun-2026 | +11 wd | — | — |
| A3840 | Elevator Testing and Commissioning | 22-Jun-2026 | 08-Jul-2026 | +11 wd | — | — |
| A3380 | Interior Aluminum/Glazing Screens Mock-up | 01-May-2026 | 19-May-2026 | +11 wd | — | — |
| A3340 | ACT Baffles Mock-ups | 10-Apr-2026 | 27-Apr-2026 | +11 wd | — | — |
| A3400 | Paint Mock-up | 05-May-2026 | 21-May-2026 | +11 wd | — | — |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 14-Jul-2025 | 29-Jul-2025 | +11 wd | — | — |
| A3290 | Mech. & Plumbing rough-ins | 01-Apr-2026 | 15-Apr-2026 | +10 wd | — | — |
| A3310 | Sprinkler Rough-ins | 01-Apr-2026 | 15-Apr-2026 | +10 wd | — | — |
| A3540 | Painting | 20-May-2026 | 02-Jun-2026 | +9 wd | — | — |
| A2610 | Erect Structural Steel | 20-Oct-2025 | 31-Oct-2025 | +9 wd | — | — |
| A2650 | Install Level 2 & 3 Decking | 03-Nov-2025 | 14-Nov-2025 | +9 wd | — | — |
| A3450 | Mech. & Plumbing rough-ins | 16-Apr-2026 | 29-Apr-2026 | +9 wd | — | — |
| A3480 | Blocking Installation | 23-Apr-2026 | 06-May-2026 | +9 wd | — | — |
| A3500 | Gypsum board Installation | 30-Apr-2026 | 13-May-2026 | +9 wd | — | — |
| A3460 | Electrical, FA & Comms rough-ins | 20-Apr-2026 | 01-May-2026 | +9 wd | — | — |
| A3510 | Drywall Taping and Mudding | 14-May-2026 | 28-May-2026 | +9 wd | — | — |
| A3530 | Interior Glazing Installation | 22-May-2026 | 04-Jun-2026 | +9 wd | — | — |
| A3590 | Electrical, FA & Comms rough-ins | 27-Apr-2026 | 08-May-2026 | +9 wd | — | — |
| A3580 | Mech. & Plumbing rough-ins | 09-Apr-2026 | 22-Apr-2026 | +9 wd | — | — |
| A3610 | Blocking Installation | 04-May-2026 | 15-May-2026 | +9 wd | — | — |
| A3470 | Sprinkler Rough-ins | 16-Apr-2026 | 29-Apr-2026 | +9 wd | — | — |
| A3600 | Sprinkler Rough-ins | 09-Apr-2026 | 22-Apr-2026 | +9 wd | — | — |
| A2660 | Install Temporary Hoarding for Slab on Deck | 03-Nov-2025 | 14-Nov-2025 | +9 wd | — | — |
| A2620 | Structural Steel Inspection | 20-Oct-2025 | 31-Oct-2025 | +9 wd | — | — |
| A1080 | Bentonite Waterstop Data Sheet | 19-Jun-2025 | 02-Jul-2025 | +8 wd | — | — |
| A1660 | Bentonite Waterstop | 26-Jun-2025 | 09-Jul-2025 | +8 wd | — | — |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 05-Nov-2025 | 17-Nov-2025 | +8 wd | — | — |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 26-Jun-2025 | 08-Jul-2025 | +7 wd | — | — |
| A3750 | Washroom Partitions and Accessories Installation | 08-Jul-2026 | 16-Jul-2026 | +6 wd | — | — |
| A2670 | Rebar and Prep Work for Slab on Deck | 10-Nov-2025 | 18-Nov-2025 | +6 wd | — | — |
| A3110 | L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) | 26-Mar-2026 | 03-Apr-2026 | +6 wd | — | — |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | 12-Mar-2026 | 20-Mar-2026 | +6 wd | — | — |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | 05-Mar-2026 | 13-Mar-2026 | +6 wd | — | — |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | 05-Mar-2026 | 13-Mar-2026 | +6 wd | — | — |
| A3720 | Ceiling/Wall Fixtures Installation | 30-Jun-2026 | 09-Jul-2026 | +6 wd | — | — |
| A3740 | Millwork Installation | 23-Jun-2026 | 02-Jul-2026 | +6 wd | — | — |
| A3710 | Tiling and rubber flooring Installation | 30-Jun-2026 | 09-Jul-2026 | +6 wd | — | — |
| A3670 | Painting | 16-Jun-2026 | 24-Jun-2026 | +6 wd | — | — |
| A3770 | Corner Guards and Wall Protection Installation | 06-Jul-2026 | 14-Jul-2026 | +6 wd | — | — |
| A3660 | Interior Glazing Installation | 09-Jun-2026 | 17-Jun-2026 | +6 wd | — | — |
| A3650 | Door and Hardware Installation | 16-Jun-2026 | 24-Jun-2026 | +6 wd | — | — |
| A3630 | Gypsum board Installation | 19-May-2026 | 27-May-2026 | +6 wd | — | — |
| A3640 | Drywall Taping and Mudding | 02-Jun-2026 | 10-Jun-2026 | +6 wd | — | — |
| A2850 | Exterior Cladding Site Measure and Scanning | 06-Mar-2026 | 16-Mar-2026 | +6 wd | — | — |
| A2940 | Exterior Cladding Site Measure and Scanning | 13-Mar-2026 | 23-Mar-2026 | +6 wd | — | — |
| A3020 | Exterior Cladding Site Measure and Scanning | 06-Mar-2026 | 16-Mar-2026 | +6 wd | — | — |
| A3100 | Glazing Shop Fabrication | 19-Mar-2026 | 27-Mar-2026 | +6 wd | — | — |
| A3120 | Exterior Cladding Site Measure and Scanning | 27-Mar-2026 | 06-Apr-2026 | +6 wd | — | — |
| A3760 | Plumbing Washroom Fixtures Installation | 08-Jul-2026 | 16-Jul-2026 | +6 wd | — | — |
| A3730 | Millwork Mock-up | 17-Jun-2026 | 25-Jun-2026 | +6 wd | — | — |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | 06-Mar-2026 | 16-Mar-2026 | +6 wd | — | — |
| A3700 | Tiling & Rubber & Carpet Flooring Mock-up | 17-Jun-2026 | 25-Jun-2026 | +6 wd | — | — |
| A1370 | 23 74 13 - Air Handling Units (R0) | 11-Jul-2025 | 21-Jul-2025 | +6 wd | — | — |
| A2030 | 23 81 26 - Split System | 18-Nov-2025 | 26-Nov-2025 | +6 wd | — | — |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 21-Apr-2026 | 29-Apr-2026 | +6 wd | — | — |
| A2680 | Concrete pour for slab on deck level 2 & 3 | 13-Nov-2025 | 20-Nov-2025 | +5 wd | — | — |
| A2960 | L2 & L3 Cladding Installation (EW2) | 11-May-2026 | 19-May-2026 | +5 wd | — | — |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | 04-May-2026 | 11-May-2026 | +5 wd | — | — |
| A3040 | L2 & L3 Cladding Installation (EW2) | 04-May-2026 | 11-May-2026 | +5 wd | — | — |
| A3050 | Horizontal Shading Louvers | 11-May-2026 | 19-May-2026 | +5 wd | — | — |
| A2900 | Air Vapor Barrier Installation | 13-Jan-2026 | 20-Jan-2026 | +5 wd | — | — |
| A3140 | L1, L2 & L3 Cladding Installation (EW2, EW2A) | 02-Jun-2026 | 09-Jun-2026 | +5 wd | — | — |
| A3070 | L1, L2 & L3 Air Vapor Barrier Installation | 25-Feb-2026 | 05-Mar-2026 | +5 wd | — | — |
| A2690 | Final Grading and Vapor Barrier for SOG | 18-Nov-2025 | 25-Nov-2025 | +5 wd | — | — |
| A2860 | Exterior Cladding Shop Fabrication | 06-Apr-2026 | 13-Apr-2026 | +5 wd | — | — |
| A2910 | Glazing Site Measure and Scanning | 07-Jan-2026 | 14-Jan-2026 | +5 wd | — | — |
| A2950 | Exterior Cladding Shop Fabrication | 13-Apr-2026 | 20-Apr-2026 | +5 wd | — | — |
| A3000 | Glazing Shop Fabrication | 26-Feb-2026 | 06-Mar-2026 | +5 wd | — | — |
| A3030 | Exterior Cladding Shop Fabrication | 06-Apr-2026 | 13-Apr-2026 | +5 wd | — | — |
| A3130 | Exterior Cladding Shop Fabrication | 27-Apr-2026 | 04-May-2026 | +5 wd | — | — |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | 25-Feb-2026 | 05-Mar-2026 | +5 wd | — | — |
| A1420 | 23 57 00 - Heat Exchangers | 25-Jun-2025 | 03-Jul-2025 | +5 wd | — | — |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 15-Jul-2025 | 22-Jul-2025 | +5 wd | — | — |
| A2970 CP | L2 & L3 Framing and Sheathing Installation | 27-Jan-2026 | 02-Feb-2026 | +4 wd | — | — |
| A3060 CP | L1, L2 & L3 Framing and Sheathing Installation | 18-Feb-2026 | 24-Feb-2026 | +4 wd | — | — |
| A2980 | L2 & L3 Air Vapor Barrier Installation | 03-Feb-2026 | 09-Feb-2026 | +4 wd | — | — |
| A1070 | Foundation Concrete Mix Design | 19-Jun-2025 | 25-Jun-2025 | +4 wd | — | — |
| A1650 | Foundation Concrete Mix Design | 23-Jun-2025 | 27-Jun-2025 | +4 wd | — | — |
| A2830 | Glazing Shop Fabrication | 21-Jan-2026 | 27-Jan-2026 | +4 wd | — | — |
| A2920 | Glazing Shop Fabrication | 04-Feb-2026 | 10-Feb-2026 | +4 wd | — | — |
| A2990 | Glazing Site Measure and Scanning | 28-Jan-2026 | 03-Feb-2026 | +4 wd | — | — |
| A3090 | Glazing Site Measure and Scanning | 19-Feb-2026 | 25-Feb-2026 | +4 wd | — | — |
| A3230 | Fire Spraying & Intumescent Paint Mock-up | 19-Feb-2026 | 25-Feb-2026 | +4 wd | — | — |
| A1510 | 23 00 00 - Wall Fin Heater | 06-Aug-2025 | 12-Aug-2025 | +4 wd | — | — |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 25-Jul-2025 | 31-Jul-2025 | +4 wd | — | — |
| A2100 | 23 00 00 - Wall Fin Heater | 12-Dec-2025 | 18-Dec-2025 | +4 wd | — | — |
| A1040 | Permit (Not Required Per Ontario Community College) | 13-May-2025 | 16-May-2025 | +3 wd | — | — |
| A1030 | IFC Drawings Released | 12-May-2025 | 15-May-2025 | +3 wd | — | — |
| A1150 | Built-up Roofing Shop Drawings | 04-Jul-2025 | 09-Jul-2025 | +3 wd | — | — |
| A1170 | Air Barrier System Data Sheet and Mockup | 04-Jul-2025 | 09-Jul-2025 | +3 wd | — | — |
| A1190 | Fire-resistive Material Data Sheet | 04-Jul-2025 | 09-Jul-2025 | +3 wd | — | — |
| A1350 | Sprinkler & Standpipe Shop Drawings | 11-Jul-2025 | 16-Jul-2025 | +3 wd | — | — |
| A1730 | Built-up Roofing | 18-Aug-2025 | 21-Aug-2025 | +3 wd | — | — |
| A1750 | Air Barrier System | 18-Jul-2025 | 23-Jul-2025 | +3 wd | — | — |
| A1770 | Fire-resistive Material | 04-Aug-2025 | 07-Aug-2025 | +3 wd | — | — |
| A1940 | Sprinkler & Standpipe Shop Drawings | 04-Aug-2025 | 07-Aug-2025 | +3 wd | — | — |
| A2710 | Concrete Pour and Curing for SOG | 28-Nov-2025 | 03-Dec-2025 | +3 wd | — | — |
| A2700 | Rebar Installation for SOG | 21-Nov-2025 | 26-Nov-2025 | +3 wd | — | — |
| A3190 | Hoisting Roof Equipment | 09-Jun-2026 | 12-Jun-2026 | +3 wd | — | — |
| A3200 | Roof Anchor System Installation | 16-Jun-2026 | 19-Jun-2026 | +3 wd | — | — |
| A1390 | 23 25 00 - Buffer Tanks | 27-Jun-2025 | 03-Jul-2025 | +3 wd | — | — |
| A1400 | 23 21 16 - Air Separator | 27-Jun-2025 | 03-Jul-2025 | +3 wd | — | — |
| A1410 | 23 21 16 - Expansion Tanks | 27-Jun-2025 | 03-Jul-2025 | +3 wd | — | — |
| A1520 | 23 74 13 - Air Source Heat Pump | 14-Jul-2025 | 17-Jul-2025 | +3 wd | — | — |
| A2110 | 23 74 13 - Air Source Heat Pump | 02-Jun-2026 | 05-Jun-2026 | +3 wd | — | — |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | 12-Jun-2025 | 16-Jun-2025 | +2 wd | — | — |
| A1010 | Contract Award | 30-Apr-2025 | 02-May-2025 | +2 wd | — | — |
| A2230 | Ontario Community College Auto Show | 05-Jun-2025 | 09-Jun-2025 | +2 wd | — | — |
| A2270 | Excavation for Under Pinning | 19-Jun-2025 | 23-Jun-2025 | +2 wd | — | — |
| A2250 | Tree Removal, Protection and Equipment Mobilization | 13-Jun-2025 | 17-Jun-2025 | +2 wd | — | — |
| A2260 | Top Soil Stripping | 18-Jun-2025 | 20-Jun-2025 | +2 wd | — | — |
| A2300 | Setup Hoarding @ Vestibule F100 | 16-Jun-2025 | 18-Jun-2025 | +2 wd | — | — |
| A2320 | Demolition of Existing Vestibule F100 | 23-Jun-2025 | 25-Jun-2025 | +2 wd | — | — |
| A2290 | Existing Structure Under Pinning | 11-Jul-2025 | 15-Jul-2025 | +2 wd | — | — |
| A2330 | Gas Meter and Pipe Relocation Investigation | 17-Jun-2025 | 19-Jun-2025 | +2 wd | — | — |
| A2340 | Gas Meter and pipe Relocation | 19-Jun-2025 | 23-Jun-2025 | +2 wd | — | — |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | 03-Jul-2025 | 07-Jul-2025 | +2 wd | — | — |
| A1020 | Subcontract Award | 29-May-2025 | 02-Jun-2025 | +2 wd | — | — |
| A1140 | Millwork Shop Drawings | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1200 | Hollow Metal Frames & Doors Shop Drawings | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1240 | Aluminum Framed Glazing System Shop Drawings | 04-Aug-2025 | 06-Aug-2025 | +2 wd | — | — |
| A1250 | Finished Hardware Schedule | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1260 | Stud framing and Gypsum Board Data Sheets | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1270 | Tiling Data sheet and samples | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1300 | Flooring Data Sheets and Samples | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1310 | Paint Drawdowns | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1320 | Washroom accessories and Partitions Shop Drawings | 25-Jul-2025 | 29-Jul-2025 | +2 wd | — | — |
| A1610 | Concrete Mix for Hardscapes | 04-Aug-2025 | 06-Aug-2025 | +2 wd | — | — |
| A1620 | Landscape Shop Drawings | 04-Aug-2025 | 06-Aug-2025 | +2 wd | — | — |
| A1720 | Millwork | 07-Oct-2025 | 09-Oct-2025 | +2 wd | — | — |
| A1780 | Hollow Metal Frames | 23-Sep-2025 | 25-Sep-2025 | +2 wd | — | — |
| A1830 | Aluminum Framed Glazing Systems | 26-Nov-2025 | 28-Nov-2025 | +2 wd | — | — |
| A1840 | Finished Hardware | 03-Dec-2025 | 05-Dec-2025 | +2 wd | — | — |
| A1850 | Stud framing & gypsum board | 04-Aug-2025 | 06-Aug-2025 | +2 wd | — | — |
| A1860 | Tiling | 09-Sep-2025 | 11-Sep-2025 | +2 wd | — | — |
| A1890 | Flooring | 22-Oct-2025 | 24-Oct-2025 | +2 wd | — | — |
| A1900 | Paint Drawdowns | 11-Aug-2025 | 13-Aug-2025 | +2 wd | — | — |
| A1910 | Washroom accessories and Partitions | 02-Sep-2025 | 04-Sep-2025 | +2 wd | — | — |
| A2200 | Concrete for Hardscape | 11-Aug-2025 | 13-Aug-2025 | +2 wd | — | — |
| A2210 | Landscape (unit pavers, furniture, etc) | 29-Oct-2025 | 31-Oct-2025 | +2 wd | — | — |
| A3780 | Layout for Elevator Cylinder | 19-Jun-2025 | 23-Jun-2025 | +2 wd | — | — |
| A3790 | Drilling Elevator Cylinder from Grade | 20-Jun-2025 | 24-Jun-2025 | +2 wd | — | — |
| A3800 | Install Steel Casing into the ground | 23-Jun-2025 | 25-Jun-2025 | +2 wd | — | — |
| A1690 CP | Structural Reinforcement | 16-Sep-2025 | 18-Sep-2025 | +2 wd | — | — |
| A1790 | Hollow Metal Doors | 22-Oct-2025 | 24-Oct-2025 | +2 wd | — | — |
| A2370 | Bulk Excavation to U/S of Footings | 18-Jul-2025 | 22-Jul-2025 | +2 wd | — | — |
| A2380 | Bulk Excavation to U/S North Stair Footing | 21-Jul-2025 | 23-Jul-2025 | +2 wd | — | — |
| A2310 | Relocate FAA | 16-Jun-2025 | 17-Jun-2025 | +1 wd | — | — |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | 14-Jul-2025 | 11-Jul-2025 | -1 wd | — | — |
| A1360 | 23 82 19 - Fan Coil Units (R0) | 04-Jul-2025 | 03-Jul-2025 | -1 wd | — | — |
| A1340 | Hydraulic Lift Shop Drawings | 11-Jul-2025 | 09-Jul-2025 | -2 wd | — | — |
| A1930 | Hydraulic Lift | 03-Dec-2025 | 01-Dec-2025 | -2 wd | — | — |
| A4010 | Underground Plumbing Rough-ins | 21-Jul-2025 | 16-Jul-2025 | -3 wd | — | — |
| A1380 | 23 21 23 - Pumps (R0) | 09-Jul-2025 | 04-Jul-2025 | -3 wd | — | — |
| A2390 | Subgrade Inspection | 25-Jul-2025 | 22-Jul-2025 | -3 wd | — | — |
| A2400 | Subgrade Preparation | 28-Jul-2025 | 23-Jul-2025 | -3 wd | — | — |
| A2410 | Soil Bearing Capacity Inspection | 29-Jul-2025 | 24-Jul-2025 | -3 wd | — | — |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | 28-Jul-2025 | 23-Jul-2025 | -3 wd | — | — |
| A2450 | Rebar for Pad Footings | 29-Jul-2025 | 24-Jul-2025 | -3 wd | — | — |
| A2460 | Rebar Inspection | 30-Jul-2025 | 25-Jul-2025 | -3 wd | — | — |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | 31-Jul-2025 | 28-Jul-2025 | -3 wd | — | — |
| A2490 | Concrete Field Testing | 31-Jul-2025 | 28-Jul-2025 | -3 wd | — | — |
| A2040 | 22 13 29 - Sump Pumps | 14-Aug-2025 | 08-Aug-2025 | -4 wd | — | — |
| A2360 | Ductbank Shoring | 17-Jul-2025 | 08-Jul-2025 | -7 wd | — | — |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | 26-Jun-2025 | 17-Jun-2025 | -7 wd | — | — |
| A2190 | 28 31 00 - Fire Alarm | 05-Nov-2025 | 27-Oct-2025 | -7 wd | — | — |
| A1480 | 23 00 00 - Exhaust Fans (R0) | 06-Aug-2025 | 22-Jul-2025 | -11 wd | — | — |
| A1490 | 23 00 00 - Unit Heater | 06-Aug-2025 | 22-Jul-2025 | -11 wd | — | — |
| A1640 | Foundation Concrete Rebar | 04-Jul-2025 | 13-Jun-2025 | -14 wd | — | — |
| A2420 | Form and Pour North Exit Stair | 25-Sep-2025 | 05-Sep-2025 | -14 wd | — | — |
| A1630 | Ductbank Underpinning | 19-Jun-2025 | 28-May-2025 | -16 wd | — | — |
| A1450 | 22 13 29 - Sump Pumps (R0) | 24-Jun-2025 | 02-Jun-2025 | -16 wd | — | — |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | 01-Aug-2025 | 03-Jul-2025 | -21 wd | — | — |
| A2080 | 23 00 00 - Unit Heater | 12-Dec-2025 | 11-Nov-2025 | -23 wd | — | — |
| A2600 | Compaction Inspection | 19-Sep-2025 | 15-Aug-2025 | -24 wd | — | — |
| A2070 | 23 00 00 - Exhaust Fans | 12-Dec-2025 | 03-Nov-2025 | -29 wd | — | — |